Firstly,

1. Burnt the fuse. After testing, the resistance of the fuse is infinite.

2. The lightning protection module is damaged. After testing, the surge protector has been broken down, causing resistance between one of the three-phase circuits and the ground wire。

The main reason is the short circuit caused by the surge protector, which causes the fuse to blow; and the root cause is wrong wire connection. at this time, you need to ask solar power contractor to change the fuse and surge protector.

Secondly, grounding fault

at this time, The inverter stops working or the AC circuit breaker in the grid connected distribution cabinet tripped. after the voltage testing, you can see, The connecting wire of a component in the middle of the photovoltaic string is connected to the photovoltaic bracket. It is possible that the insulation layer of the cable is damaged. The nominal open circuit voltage of the component is 40V. This photovoltaic string has a total of 9 components, and from the detected data, it may be the connection line between the 4th and 5th components and the bracket connection.

and its related solution is to heck the connection wires of the components, paying special attention to the areas where the connection wires come into contact with the bracket, and identify the wires that are connected to the bracket,

Thirdly, Breakage of solar panles

all kinds of factors caused the breakage of solar panels; The output current of photovoltaic modules decreases, reducing the system output power. and its associated solution is to ask engineers of solar power contractor to replace a new solar panel.

Fouth, Abnormal voltage level of solar string in an open circuit.

The output voltage of the photovoltaic array is too low, which reduces the output power of the system, and its further damage can cause component breakdown for a long time.

and its coresponsing solution is to Detect the open circuit voltage of each component in the string, identify the component with abnormal open circuit voltage, check its bypass diode, replace the diode if there is a problem, and replace the component if there is no problem with the diode.

Finally, combiner box and transformer was both burnt;

It may be due to an internal short circuit in the circuit breaker or surge protector causing excessive current or some other reasons, which need engineers of your solar power contractor to do on-site evaluation.

distributed PV power plant

As a professinal & experienced solar power contractor in China, we are able to provide you a package solution for your new solar power plant, from original energy need and its capacity, checking all conditions of your site, primary design of the solar power plant, choosing right materials to install, including solar panels, inverters, solar energy battery storage, PV cable and power cables, power transformers etc, installation and connection to local power grid network.